ProjecT Milestones

  1. March 2, 2015 RFP Submitted

  2. July 29, 2015 MarKa recommended by TAC and Mayor approves recommendation

  3. September 28, 2015 Community Meeting 1 – Introductions and Charrette

  4. October 21, 2015 Community Meeting 2 – Presentation of Project with Q&A

  5. November 10, 2015 Community Meeting 3 – Design Presented with Changes from Q&A

  6. December 9, 2015 Community Meeting 4 – Focused on Park Design

  7. April 28, 2016 Design Review Committee First Hearing

  8. May 5, 2016 Zoning Ordinance amendment heard in a Joint Public Hearing of BOA Land Use Committee and Planning Board

  9. May 18, 2016 Land Disposition Agreement (“LDA”) heard by BOA Finance Committee Hearing

  10. May 26, 2016 Design Review Committee Second Hearing

  11. June 2, 2016 Entitlement Permit Joint Public Hearing of Planning Board and Board of Alderman Land Use Committee of the Whole

  12. June 21, 2016 Land Disposition Agreement (“LDA”) is executed by the Mayor following Board of Alderman review with subcommittee involvement

  13. June 23, 2016 Design Review Committee Third Hearing

  14. June 23, 2016 Zoning Ordinance amended by vote of the Board of Aldermen (unanimous)

  15. August 4, 2016 Entitlement Permit Application first reviewed by Planning Board

  16. August 8, 2016 Entitlement Permit Decision approved by Planning Board (unanimous)

  17. September 26, 2016 Affordable Housing Implementation Plan (AHIP) executed

  18. October 22, 2016 Entitlement Permit Recorded at Registry of Deeds

  19. October 28, 2016 Schematic Design Milestone Set Completed

  20. November 16, 2016 Community Meeting 5 – Park Design Unveiled

  21. November 22, 2016 Land Acquired from City

  22. January 11, 2017 Community Meeting 6 - Construction Kick-Off Meeting

  23. March 1, 2017 Abatement & Demolition Start

  24. June 28, 2017 Building Permit

  25. July 19, 2017 Kaplan Construction onsite as General Contractor.

  26. December 20, 2017 Pricing Set Design Completion

  27. July, 2018 Construction commences

  28. October 3, 2018 - Groundbreaking Ceremony

  29. May 6,2019 - Community Meeting 7 - Park Design Informational Meeting

Construction is scheduled to conclude early 2020.